Background
A major Australian telecom operates a mission-critical data centre where continuous operation and stable cooling are vital. Vertiv found key condenser water system components—chillers, pumps, and infrastructure—nearing end-of-life. To mitigate risk, Vertiv partnered with Air Water Power (AWP) to execute a staged upgrade, carefully designed and implemented within the live facility, ensuring uninterrupted operation and service continuity throughout the condenser water system replacement.
Results
- Seamless staged replacement of end-of-life condenser water infrastructure in a live data centre.
- Continuous cooling redundancy and zero disruption to operations maintained.
- Enhanced resilience, future-ready mechanical/power systems, and EMS energy visibility.
- Reduced operational risk through proactive planning and temporary resilience measures.
| Case Summary | |
|---|---|
| Location: |
Adelaide, South Australia |
| Critical Need: |
The customer needed a staged upgrade of end-of-life chillers, pumps, and mechanical switchboards to maintain continuous operation, full cooling redundancy, and mission-critical service reliability across four technical spaces in a live data centre. |
| Vertiv Solution: |
|