Established in 2007, the ISF Group is a specialist engineering integrator with operations within Southern Africa. The group delivers projects in information and communications technology (ICT), energy and specialised projects.
Results
- Rapid deployment- The Tier III data centre in Malawi was built, tested and delivered in 28 weeks, with just seven weeks for shipping and five days for on-site assembly, cutting implementation time by more than half compared to traditional builds.
- Faster ROI, stronger market position- The rapid deployment enabled the customer to recoup investment faster and secure a competitive edge in a high-growth market.
- Scalable growth model- The modular ‘pay as you grow’ approach allows cost-effective expansion without heavy upfront capital, allowing the business to scale with customer demand.
Case Summary | |
---|---|
Location: |
Africa |
Critical Need: |
|
Vertiv Solution: |
Vertiv™ SmartMod™
|