Background
Africa's vast terrain and developing infrastructure can make consistent network uptime a challenge. Vertiv meets this with integrated power solutions engineered for reliability, energy flexibility, and sustained performance in demanding conditions.
Results
- Increased backup power
The solution extended battery backup to 48 hours—exceeding the 36-hour requirement in the RFQ. - 100% solar-powered sites
All ~100 sites now run entirely on solar energy, surpassing the client's goal of 50% renewable-powered sites and supporting global environmental responsibility targets. - Future-ready and scalable
The design allows for capacity expansion, with space built in for additional solar modules. - Fast, flexible deployment
Each site was installed in under a week, with no need for concrete or deep foundations—ideal for remote locations with limited water access. - Built for harsh conditions
The custom-built system withstands flooding and dusty environments, enabling long-term reliability in rural settings.
Case Summary | |
---|---|
Location: |
Central Africa |
Critical Need: |
'Energy poverty’ is particularly challenging in rural regions, where infrastructure is costly, funding is limited, and technical expertise is scarce. Remote, hard-to-access locations further complicate maintenance and service delivery. At the same time, growing pressure to reduce emissions and improve energy efficiency has intensified the need for renewable, eco-friendly power solutions. |
Vertiv Solution: |
|